Description of Contract Work: Trades Included: Sitework,
Concrete, Precast Concrete, Masonry, Steel, Trusses, Carpentry, Roofing, Paint,
HVAC and Electric
New Construction to relocate the South Switch House from
Building #832 to new Building #826. Work included excavation, cast-in-place
concrete foundation, CMU block wall with brick veneer, concrete slab on grade
and sidewalk, precast concrete planks, carpentry, gypsum wallboard, doors &
hardware, painting, synthetic slate shingle roof, and removal and disposal of
existing switchgear from old building. New electrical work included basic
electric and new 5KV metal clad switchgear and breakers, underground conduit,
cable, supports and lightning protection.
|