Halon, HVAC and Roof Replacement, Building 2101, Spellman Hall U.S. Military Academy, West Point, NY
PAST PERFORMANCE & REFERENCE SHEET
Project Name & Location: |
Halon, HVAC and Roof Replacement, Building 2101, Spellman Hall, U.S. Military Academy, West Point, NY |
Client Name & Address: |
Department of the Army, NY District, Corps of Engineers, Jacob Javits Federal Building, 26 Federal Plaza, New York, NY 10278 |
Contract Number: |
DACA51-03-C-0006 |
Contract Duration: |
335 Days |
Date of Contract: |
02/21/2003 |
Notice to Proceed Date: |
03/04/2003 |
Initial Completion Date: |
02/10/2004 |
Revised Completion Date: |
11/12/2004 |
|
|
|
|
Description of Contract Work: |
Halon, HVAC and Roof Replacement project at U.S. Military Academy, West Point, NY, inclusive of: |
- Demolition (all trades) - Structural Steel - Acoustical ceilings - Computer Flooring - Fire Reporting System - Radio - Wet Pipe Sprinkler System - HVAC System w/ Digital Controls - Interior & Exterior Electrical Work - Lightning Protection |
- Site & concrete works - Roofing - Painting - Elevator upgrade - Fire Detection & Alarm System - Addressable - Cycling Preaction Sprinkler System - Plumbing - Diesel Generator Set and Automatic Transfer Switches - Underground electrical distribution system |
The works include providing all required civil, architectural, specialties, fire protection sprinkler system, electrical and fire detection & alarm system, plumbing works, elevator upgrade, generator, lightning protection, and underground electrical distribution system to renovate and upgrade Spellman Hall, consisting of the Academy� s computer center and office wing with five floors.
All works have been accomplished within occupied and 24/7 operational computer area, workshop area and office wing while the academy personnel were facilitating the buildings. Works have been phased in four sections to allow the installation of new HVAC, roofing sprinkler and fire alarm system and switching from existing systems without any power, HVAC and fire protection and alarm. Successful phasing and scheduling was a crucial part of the project as this building is the �brain� of the academy containing all electronic data and classified information. Collette Contracting has performed the construction operations simultaneously in all areas and phases in a very professional manner without disturbing the building occupants without a single complaint. As always, Collette has paid special attention to dust and noise protection and such operations have been performed by close coordination with Fire Department, building occupants and maintenance department. In spite of various revisions and additions, the project is currently scheduled to be completed earlier than contractual completion date.
There was no accident or loss time since the project commencement. Collette Contracting�s performance has surpassed all contract requirements and exceeded many to the government�s benefit.
|
|
|
Generator pad foundation & u.g. conduit |
Generator lifting & operation | |
|
|
generator installed on pad |
roofing works in progress |
|
|
computer flooring prep for AC units |
Liebert computer AC units installation |
|
|
typical Liebert computer AC unit |
Liebert computer AC unit piping installation |
|
transfer switch pad with underground conduit | |