Renovation of Building 151, Phase # 1 Picatinny Arsenal, NJ
CURRENT PERFORMANCE & REFERENCE SHEET
Project Name & Location: |
Renovation of Building 151, Phase # 1 Picatinny Arsenal, NJ |
Client Name & Address: |
U.S. Army Corps. Of Engineers, Baltimore District 10 South Howard Street Baltimore, MD 21201 |
Contract Number: |
W912DR-07-D-0027-0002 |
Contract Duration: |
180 Days |
Date of Contract: |
09/27/2007 |
Notice to Proceed Date: |
10/24/07 |
Contractual Completion Date: |
07/07/2008 |
Date Work Completed: |
07/07/2008 |
|
|
|
|
Description of Contract Work: |
Renovation of Building 151, Phase # 1 Picatinny Arsenal, New Jersey Inclusive of:
- Demolition
- Carpentry
- Asbestos Abatement
- Electrical Works
- Demolish existing tile wainscoting throughout all areas
- Demolish partition floor to ceiling.
- Remove old door and block opening. Create opening for new door.
- Remove wall mounted unit heaters and piping.
- Cap exposed piping left for reconnection and removed all lath chases surrounding related piping.
- Performed Asbestos Abatement.
- Relocated the Water Main.
- Relocate the Electric Panel.
- Poured new concrete slab for floor.
|